New Water Supply Scheme for Malegaon City

Water & Wastewater

Project Title : New Water Supply Scheme for Malegaon City under UIDSSMT
Client : Malegaon Municipal Corporation, Malegaon
Project Cost : Rs. 51.76 Cr.
Project Brief : Development of New Water Supply Scheme (Girna Dam as source) for Malegaon City under UIDSSMT, including Distribution Network, Water Treatment Plant (WTP) of 71 MLD Capacity, ESRs at various locations in the City, Raw Water Rising Mains, Pumping Machinery, Transmission Mains, Distribution main network of total length 153.91 KM of 100 mm to 600 mm dia Pipe.
Scope :
  • Detailed Survey & Investigation
  • Structural Design & Engineering
  • Detailed Cost Estimation
  • Detailed Project Report
  • Detailed Financial Analysis
  • Government Approvals